Relevant Factors in Grant of Freezing Injunction in Support of Foreign Arbitration
2
Suit Can Proceed Against General Contractor Based on Claims of Subcontractor’s Negligence and Public Nuisance

Relevant Factors in Grant of Freezing Injunction in Support of Foreign Arbitration

Mobil Cerro Negro Ltd. v. Petroleos de Venezuela SA, 2008 WL 678144, [2008] EWHC 532 (Queen’s Bench Div., Commercial Ct.)

In this case, a freezing injunction was set aside, having been granted in support of claims which were the subject of ICC arbitration seated in New York.  The parties were parties to a contract for the exploitation of oil rights, the Claimant being a US corporate and the Defendant the Venezuelan state oil company.  Venezuelan legislation passed in 2007 mandated the “migration” of non-Venezuelan interests in Venezuelan oil to Venezuelan entities, and gave rise to claims under the parties’ contract.  Mobil obtained a worldwide freezing injunction up to a value of $12 billion and Petroleos applied to have the injunction set aside. Read More

Suit Can Proceed Against General Contractor Based on Claims of Subcontractor’s Negligence and Public Nuisance

New York v. Shaw Contract Flooring Servs., 853 N.Y.S.2d 694 (N.Y. App. Div. 2008)

State university brought claims against a general contractor and subcontractor for asbestos released as a result of tile work performed by the subcontractor.  The trial court denied the general contractor’s motion to dismiss the negligence and public nuisance claims.  The Appellate Division affirmed. Read More