Archive:2008

1
Court holds Surety has Common Law Claim for Indemnity Against Subcontractor, Despite Absence of Privity
2
Statute of Limitations for Contractor Negligence and Breach of Warranties Does Not Accrue until Turnover of Control of Condo Association to Unit Owners
3
Under Business and Professions Code § 7031, Contractor Must be Licensed Prior to Preparing Shop Drawings or Ordering Materials for Construction Project
4
Discretionary Right to Adjudicate No Basis for Stay of Arbitration
5
Partial Enforcement of Award Which Has Not Yet Become Final
6
Appellate Court Finds Liquidated-damages Clause Was Not a Penalty and Thus Was Enforceable
7
Subcontractor’s Contractual Indemnity Obligation to Contractor for EIFS Damage Not Covered by Indemnity Provisions of Texas Product Liability Act
8
Insurer’s Duty to Defend Construed Broadly in Favor of Insured
9
No Requirement to Dispense with Leave to Appeal Arbitral Award Under Section 69
10
Constructive Notice Not Established by Discussion in Meetings

Court holds Surety has Common Law Claim for Indemnity Against Subcontractor, Despite Absence of Privity

J.C. Gibson Plastering Co. v. XL Specialty Ins. Co., 2008 WL 1931348 (M.D. Fla. May 2, 2008)

In J.C. Gibson Plastering, the U.S. District Court for the Middle District of Florida held that a surety could state a claim for common law indemnity against a subcontractor despite the absence of privity.  The court found that the two elements necessary to state a claim for common law indemnity were satisfied:  (i) the surety may be constructively, vicariously or derivatively liable for the subcontractor’s failure to pay sub-subcontractors, and (ii) the surety was without fault in causing the loss it was required to bear, despite failing to timely respond to the claim.

Also, despite the lack of Florida authority on the question, the court also held that a surety’s failure to respond to the subcontractor’s claim for payment under a payment bond within forty-five days (as required under the bond) barred the surety from challenging the claim or from asserting counterclaims to the extent the surety could have reasonably identified the bases of its affirmative defenses or counterclaims’ during the forty-five day period.  By failing to respond timely, the claim was undisputed and subject to summary judgment.

Statute of Limitations for Contractor Negligence and Breach of Warranties Does Not Accrue until Turnover of Control of Condo Association to Unit Owners

Saltponds Condo. Assoc. v. Walbridge Aldinger Co., 979 So. 2d 1240 (Fla. Dist. Ct. App. 2008)

In this case, a condo association sued a contractor in connection with alleged construction defects discovered after the control of the association passed from the developer to the unit owners.  The contractor argued that the claims were barred by the three-year “statute of limitations” set forth in Florida Statute Section 718.203.  That Section, however, merely sets the warranty period for construction improvements and materials, not the statute of limitations.

Read More

Under Business and Professions Code § 7031, Contractor Must be Licensed Prior to Preparing Shop Drawings or Ordering Materials for Construction Project

Great West Contractors, Inc. v. WSS Ind. Constr., Inc., 162 Cal. App. 4th 581 (2008)

WSS Industrial Construction, a steel subcontractor, sued general contractor Great West Contractors, to recover for work performed on a public works project in Riverside, California.  At the time that WSS submitted its bid proposal to Great West, WSS had applied for but not yet obtained a corporate contractor’s license.  WSS did receive a license after the bid was accepted, but only after it had already ordered multiple sets of shop drawings and some of the material necessary for the project.  WSS initiated the lawsuit by suing Great West and its surety, Fidelity and Deposit Company of Maryland, for $91,000 due under the contract and subsequent change orders.

At trial, Great West and Fidelity moved for a nonsuit on the grounds that WSS was statutorily barred, pursuant to Business and Professions Code section 7031, from any recovery because WSS was not duly licensed at all times during performance of the contract.  The trial court determined that WSS’s president had held valid individual licenses at all times and that, in any event, WSS was not required to have a license for the work that it performed prior to receiving its license.  The court held that “there was substantial compliance with the licensing during the contract and work was performed in good faith.”  The jury awarded WSS $220,000 in damages, including statutory penalties and interest.  Great West and Fidelity appealed after the court rejected their post-trial motions for a new trial, vacation of judgment and judgment notwithstanding the verdict. Read More

Discretionary Right to Adjudicate No Basis for Stay of Arbitration

Cubitt Bldg. & Interiors Ltd. v. Richardson Roofing (Ind.) Ltd., [2008] EWHC 1020 (Queen’s Bench Div., Tech. & Constr. Ct.)

Cubitt, the contractor on a construction project in London, engaged Richardson as sub-contractor.  Under the relevant sub-contract, both parties had a discretion to refer disputes to adjudication.  Richardson completed its works, Cubitt alleged delay and indicated that it intended to deduct liquidated damages from the amount payable to Richardson.  Richardson started arbitration proceedings against the Cubitt.  Cubitt sought a stay of the arbitration so that it could refer the dispute to adjudication. Read More

Partial Enforcement of Award Which Has Not Yet Become Final

IPCO (Nigeria) Ltd. v Nigerian Nat’l Petroleum Corp., 2008 WL 1771454, [2008] EWHC 797 (Queen’s Bench Div., Commercial Ct.)

IPCO contracted with NNPC to design and build a petroleum export terminal in Nigeria.  A dispute ensued and was arbitrated in Nigeria, subject to the supervision of the Nigerian courts.  IPCO obtained an award in October 2004 (in the sum of approximately US$152 million) and sought an order for its enforcement in England.  At the same time, NNPC brought an appeal against the award.  The English High Court granted an order to IPCO, but adjourned enforcement of the award pending the Nigerian appeal.  Subsequent developments in Nigeria had meant that any appeal against the award now lay some five or ten years in the future.  IPCO applied for a variation of the order adjourning enforcement of the award. Read More

Appellate Court Finds Liquidated-damages Clause Was Not a Penalty and Thus Was Enforceable

Mineo v. Lakeside Village of Davie, LLC, 983 So.  2d 20 (Fla. Dist. Ct. App. 2008)

Where a contract for the purchase of real property and construction of a residence gave the seller the option of retaining deposits and change order payments as liquidated damages in the event of the buyer’s default, or the seller could sue for specific performance at the purchase price plus interest as delay damages, the liquidated damages provision was not an unenforceable penalty because the contract did not provide the seller with the option to sue for actual damages (which would have change the character of the forfeiture as agreed damages).

Subcontractor’s Contractual Indemnity Obligation to Contractor for EIFS Damage Not Covered by Indemnity Provisions of Texas Product Liability Act

K-2, Inc. v. Fresh Coat, Inc., 253 S.W.3d 386 (Tex. App. 2008)

In this case, the court held that the Texas Product Liability Act did not provide a product seller with the right of indemnity against a product manufacturer for that seller’s independent liability under a contract.

Several homeowners sued their builder, its subcontractor which installed synthetic stucco cladding (EIFS) on their houses and the EIFS manufacturer after experiencing water penetration leading to structural damage.  After the claims made by the homeowners and the home builder against the subcontractor were settled, the subcontractor obtained a judgment against the manufacturer for indemnification of the amounts it paid in the settlement.  The manufacturer appealed that portion of the judgment finding it liable to indemnify the subcontractor for the amount it paid to settle the home builder’s claims because it was paid under an indemnity clause in the subcontract. It did not dispute that part of the judgment obligating it to indemnify the subcontractor for settlement of the homeowners’ claims.  Read More

Insurer’s Duty to Defend Construed Broadly in Favor of Insured

WTC Captive Ins. Co. v. Liberty Mut. Fire Ins. Co., 549 F. Supp. 2d 555 (S.D.N.Y. 2008)

After the World Trade Center disaster in September 2001, the City of New York created a captive insurance company, funded by a grant from the Federal Emergency Management Agency, to insure the costs of lawsuits arising from the WTC clean-up efforts.  Liberty Mutual was the primary insurer and had agreed to defend and indemnify the city against claims including, but not limited to, bodily and personal injury.  A group of secondary insurers agreed to provide the same coverage if the Liberty Mutual policy became exhausted.  All of the policies were retroactive to September 11, 2001. Read More

No Requirement to Dispense with Leave to Appeal Arbitral Award Under Section 69

Royal & Sun Alliance Ins. PLC v. BAE Sys. (Operations) Ltd., 2008 WL 924979, [2008] EWHC 743 (Queen’s Bench Div., Commercial Ct.)

An arbitral award pursuant to the arbitration under LCIA rules of an insurance dispute formed the subject matter of this claim.  Royal & Sun sought to appeal the award to the English court on a point of law.  The defendants argued that s.69 of the Arbitration Act 1996 (the “Act”) and the terms of the relevant arbitration agreement obliged Royal & Sun to seek the leave of the court.  The question was settled in Royal & Sun’s favour as a pure question of construction involving consideration of the Act, the LCIA rules and the arbitration agreement. Read More

Constructive Notice Not Established by Discussion in Meetings

Geonie v. O.D. & P. N.Y., Ltd., 855 N.Y.S.2d 495 (N.Y. App. Div. 2008)

An injured worker, Geonie, filed a negligence suit against multiple defendants, including the general contractor, after stepping into an opening left by the removal of a tile from a raised floor in a computer room.  Geonie argued that defendants failed to provide adequate safety devices to protect against an elevation-related hazard and failed to adequately supervise the work area.  He further claimed that because the removed tile was discussed at weekly safety meetings, the defendants had, at least, constructive notice of the problem.  The trial court dismissed Geonie’s claims under New York Labor Law and his negligence claim against the general contractor. Read More

Copyright © 2024, K&L Gates LLP. All Rights Reserved.