Catagory:Articles and Publications

1
Materials Available: 2015 Legal Update – Construction and Engineering Seminar
2
Update on Legal Advice Privilege
3
Illinois Now Allows Bonding Off of Mechanics Liens on Private Projects
4
A New Australian Standard (AS 11000) to Replace the General Conditions of Contract (AS 4000 and AS 2124)
5
Unreasonable disadvantage to contractor: Securing warranty claims by standard terms and condi-tions restricted by German Federal Supreme Court
6
Good Faith in the Middle East
7
Liquidated Damages in the UAE, Qatar, and Saudi Arabia
8
Independent evidentiary proceeding—A legal tool in Germany to avoid construction court proceedings
9
Time Bars in Construction Contracts – A Comparison between Jurisdictions
10
No Contract, No Problem: HICPA Does Not Prevent Contractors From Recovery Under A Quantum Meruit Theory

Materials Available: 2015 Legal Update – Construction and Engineering Seminar

On 7 October 2015, the K&L Gates London office held a 2015 Legal Update – Construction and Engineering breakfast seminar.  The seminar featured the following topics:

  • CDM 2015: The End of the Transition – Nicola Ellis, Special Counsel
    The Construction (Design and Management) Regulations 2015 came into force on 6 April. This session highlights the key changes that were introduced, the practical effects of those changes and the consequences of the transitional provisions coming to an end on 6 October.
  • Construction Law UpdateInga Hall, Special Counsel
    A summary of some of the recent key construction and engineering cases that have come before the courts, and the implications of those decisions.
  • The NEC3 Suite: Beyond the ECC – Matthew Smith, Partner
    This session looks at the true range of options the NEC3 suite of contracts offers and gives an insight into which issues are addressed consistently across the suite, and highlights the key differences between specific forms.

To view a copy of the materials from this seminar,  please click here.

Update on Legal Advice Privilege

By Mike R. Stewart and Nita Mistry, K&L Gates London

In common law jurisdictions, legal professional privilege prevents communications between a professional legal adviser and their clients from being disclosed.  There are two main types of privilege:

  • Legal advice privilege, which protects confidential communications between lawyers and their clients; and
  • Litigation privilege, which protects confidential communications, provided that such communications have been created for the dominant purpose of obtaining legal advice for litigation.

Read More

Illinois Now Allows Bonding Off of Mechanics Liens on Private Projects

By Jesse G. Shallcross, K&L Gates, Chicago

On July 29, 2015, Illinois Governor Bruce Rauner signed into law an amendment to the Illinois Mechanics Lien Act which allows a property owner, contractor or other party with an interest in real property which is subject to a mechanics lien claim filed against the property by an aggrieved contractor, subcontractor or material supplier on a private project to substitute a surety bond for such mechanics lien claim.[1]  The new law is scheduled to take effect on January 1, 2016.

Illinois now joins the ranks of no less than 35 other states that provide for the right of an interested party to substitute a surety bond for real property against which a mechanics lien claim is filed, also known as “bonding off” a mechanics lien claim, on private projects.

Read More

A New Australian Standard (AS 11000) to Replace the General Conditions of Contract (AS 4000 and AS 2124)

By Sandra Steele, K&L Gates, Sydney

The AS 4000 and AS 2124 General Conditions of Contract are widely used forms of procurement in the Australian construction industry. A technical committee has recently drafted a new standard form contract (AS 11000) to supersede these previous forms.

The drafters have sought to provide a balanced approach to risk allocation and have updated the standards for certain legislative changes and case law including for GST and security of payment legislation. Despite the extensive amendments, as the AS 11000 is drafted as a national standard form contract, some State and Territory specific legislation and case law has not been included.

Read More

Unreasonable disadvantage to contractor: Securing warranty claims by standard terms and condi-tions restricted by German Federal Supreme Court

By Christoph Mank, K&L Gates, Berlin

Background
Standard terms and conditions in German construction contracts often contain requirements to provide a warranty bond to secure performance by the contractor of its warranty obligations under the contract. These requirements often stipulate the contractor to provide both a performance guarantee and a warranty bond.

The warranty bond secures the contractor’s warranty obligations during the warranty period (typically arising after the acceptance and take-over of the construction works) and is often in an amount of not more than 5% of the contract sum. This practice has been established due to prior case law by the German Federal Supreme Court. According to the Federal Supreme Court, the client´s security interest after acceptance of the construction is significantly lower than its security interest during performance.

Read More

Good Faith in the Middle East

By Darran J. Jenkins, K&L Gates, Doha

The concept of good faith as applicable in the Civil law jurisdictions of Qatar and the United Arab Emirates (“UAE”) is one that may be unfamiliar to lawyers from a common law background where good faith is applies in a very limited fashion, if at all. [1]

The Position in the Middle East

The position in Qatar is set out in Article 172 of the Qatar Civil Code[2]:

1.    The contract must be performed in accordance with its contents and in a manner which consistent with the requirements of good faith.

2.    The contract is not confined to obliging a contracting party to its contents, but also includes its requirements in accordance with the law, custom and equity as per the nature of the obligation.

The corresponding article in the UAE Civil Code[3] is Article 246 which states:

“(1)     The contract must be performed in accordance with its contents, and in a manner consistent with the requirements of good faith.

(2)     The contract shall not be restricted to an obligation upon the contracting party to do that which is (expressly) contained in it, but shall also embrace that which is appurtenant to it by virtue of the law, custom, and the nature of the transaction.”

In Bahrain, Article 127 of the Civil Code[4] requires:

A contract is not only limited to its expressed conditions, but also as regards everything which according to law, usage and equity is deemed in view of the nature of the obligation, to be a necessary sequel to the contract, taking into consideration custom and usage, requirements of equity, nature of business, good faith and honesty.”

And Article 129 provides:

A contract must be performed in accordance with its contents and in compliance with the requirements of good faith and honesty.”

Each of these Civil Codes takes an almost identical approach to the treatment of good faith. As a result, a contract will not be interpreted using solely its terms but will be interpreted against the requirements of customs, equity and good faith.

The requirement to act in good faith is a strong, positive obligation on the parties to a contract.  It is not merely a requirement not to act in bad faith and not to deceive one another. Each party is instead under a legal obligation to exercise good faith in the performance of its contractual obligations and it is dealings with the other party. In a construction context, the duty of good faith would require an employer to cooperate with the contractor and deal with change requests in a timely and fair manner, whilst a contractor would be obliged to avoid delaying the performance of their works.

It is interesting to note that the obligation within the Qatar Civil Code is to perform the contract in good faith but it does not extend to negotiating the contract in good faith. The parties are free to adopt an adversarial approach to negotiation of the contract to try to obtain the best possible deal for themselves. Only once the contract has been signed does the duty to act in good faith arise.

In relation to insurance contracts, the duty to perform in good faith under the Civil Code does not in any way limit the duty of the insured to act with utmost good faith when placing the policy.  This is because the Civil Code also recognizes and enforces a higher standard of care where the parties have agreed it should apply.

[1] Please note, all English extracts in this Article are taken from an unofficial English translation of the Qatar and UAE Civil Code, reference should always be made to the original Arabic text.

[2] Law Number 22 of 2004

[3] Law Number 5 of 1985

[4] Law Number 19 of 2001

Liquidated Damages in the UAE, Qatar, and Saudi Arabia

By Harriet C. Jenkins, K&L Gates, Doha

INTRODUCTION

Liquidated Damages (LDs) are treated very differently across the Gulf region and from the position as understood within the English common law jurisdiction.

The universal starting point for LDs is in contract; parties should pre-determine the rate of damages a contractor should pay to the employer in the event of a (specified) breach, most commonly that of late completion.  For the purposes of this article, we shall consider LDs solely in the context of delay damages, whereby in the event of delay to project completion, an employer can demand a fixed compensatory sum from the contractor.

The position of the civil law jurisdiction of the Middle East is very different from that understood within the English common law system.   It is commonly accepted that English courts are generally very reluctant to look beyond the contractual position and open up any agreed position on LDs.[1]  Across the Gulf however, differing civil codes empower courts (and tribunals) to look behind the parties’ contract and adjust delay damages based upon principles of actual loss and fairness.

This article discusses the differing treatments of LDs across three Gulf jurisdictions (namely, the United Arab Emirates, Qatar and Saudi Arabia), and reveals what parties can expect in regards to their compensation for delay.[2]

Read More

Independent evidentiary proceeding—A legal tool in Germany to avoid construction court proceedings

By Christoph Mank and Eva Hugo, K&L Gates, Berlin

The dilemma

A construction principal faces a lot of questions if material defects occur while a building is still under construction: he can decide to continue with construction in order to prevent a delay in completion, but faces the risk that it might be difficult, or rather, impossible, to outline and, in particular, to later prove the background and causes of defects. Furthermore, warranty claims against contractors or architects can become time-barred if the works continue for years without clarification of the defect. On the other hand, if construction stops until a court proceeding takes place, the project might be delayed due to the excessive duration of German construction court proceedings, possibly causing enormous financial losses. Besides the principal, contractors and architects also have an interest in the causes and responsibility for an occurring, material construction defect being promptly clarified and assessed.

Aims of independent evidentiary proceedings

Independent evidentiary proceedings, as provided in the German Code of Civil Procedure, can help those principals, contractors and architects involved in construction project to step out of the above scenarios.

Independent evidentiary proceedings are initiated by the application of one party. It is not required that a court proceeding be pending. Independent evidentiary proceedings aim to secure the state of construction and to clarify the causes of, and responsibilities for, a defect through an expert’s participation. This enables construction parties, for example, the principal and a contractor, to come to an agreement and to avoid a subsequent court proceeding. The defect can be remedied and the project continued to completion. Even if an agreement cannot be reached and a court proceeding follows, an independent evidentiary proceeding will help accelerate the construction court proceeding, because the independent evidentiary proceeding’s results will be considered as evidence in the court proceeding.

Legal requirements

Independent evidentiary proceedings have to be applied for at the court that would also settle the legal matter. Furthermore, the applicant party has to provide a legitimate interest to establish the state or value of an object, the cause of property damage or a material defect or the effort required to remedy the property damage or material defect by a written expert opinion. Such a legitimate interest is statutorily presumed if the establishment serves to avoid a court proceeding.

Evidence can be taken by way of written expert opinion. In its application, the applicant has to precisely designate the opponent, as well as the facts and circumstances on which evidence should be taken; it is not allowable to describe vague, unsubstantiated facts only for the purpose of obtaining information to concretize an argument of fact. However, it is permitted to describe the facts as they appear to the applicant as a lay person in construction matters. The court then decides whether to take evidence on the application, and chooses an expert to be instructed. The expert´s opinion only assesses the case on a factual basis; legal questions and interpretations are excluded.

Independent evidentiary proceedings end with the delivery of the expert´s opinion and, possibly, with an agreement between the parties, which then will be recorded by the court, but not by a contentious decision of the court. The court may set a time period within which the parties can raise objections to the expert´s opinion and may apply for appointments to orally discuss the opinion with the expert.  If, however, the case is later brought before court by one of the parties as the result of the independent evidentiary proceedings, the expert´s opinion will be treated as if it was obtained during the court proceeding.

The opening of an independent evidentiary proceeding also affects the underlying claims. The limitation of those claims, especially warranty claims, will be suspended from the beginning of the independent evidentiary proceeding until six months after its end, a further advantage of this special type of proceeding.

 

Time Bars in Construction Contracts – A Comparison between Jurisdictions

By Jafar S. Khan, K&L Gates, Doha and Inga K. Hall, K&L Gates, London

The consequences for a contractor who delays in submitting an application for an extension of time, or who gets his payment application in late, can differ dramatically depending on the contract terms and also the governing law of the contract.

In order to ensure contractors submit their claims as they arise (rather than ‘roll them over’ to the end of a project) and to assist in efficient cash-flow management, it is common practice for both bespoke and standard form contracts to include express procedures for submitting claims for time, money or other relief. Provisions dealing with claims for an extension of time for example will frequently stipulate time limits for each of the following:

  • the initial notification of the events giving rise to the claim,
  • submission of particulars,
  • a response/request for further particulars on behalf of the employer, and
  • an assessment of what if any extension should be awarded.

What happens though if one of the parties does not complete the relevant action or step forming part of the procedure within the stipulated time?

This will depend first on what the contract says the consequences are to be. The usual practice in the standard forms mentioned above is to expressly provide that a failure to (say) submit the particulars of the claim strictly in accordance with the time period prescribed will invalidate the claim i.e the claim becomes “time barred”. Looked at in another way, such express provisions are seeking to make timely submission of the required particulars a condition precedent to recovery.

This raises the interesting question of whether such time bars are enforceable. On the one hand it would seem disproportionate to bar a substantial claim if a contractor was only one day late in filing its claim, but on the other hand, an employer might have made certain assessments as to liability and closed its position with respect to issues in relation to the events surrounding the claim. It would arguably be unfair to ignore the terms of the contract and permit the employer to continue to be exposed to claims.

The issue of enforceability will depend to a significant extent on the law of the contract. In common law systems such as the United Kingdom for example, clearly drafted time bars (such as those found in FIDIC sub-clause 20.1 and NEC3 clause 61.3) have in the past generally been enforced.

An issue which is however currently generating debate in the UK is how to properly assess the time period for first notifying an event. NEC3 clause 61.3 states that if the contractor does not notify a compensation event (i.e a variation) “within 8 weeks of becoming aware of the event, he is not entitled to a change in the Prices [or] the Completion Date”. FIDIC sub-clause 20.1 requires the contractor to give notice “as soon as practicable and not later than 28 days after the contractor became aware, or should have become aware of the event or circumstance [giving rise to the claim]”. Although both clearly state the condition precedent aspect of the timely giving of notice, the more difficult issue is when does that time start running?

There is frequently a delay between the time an event occurs, and when the effect of that event as giving rise to a claim is identified. Equally, for an ongoing event which spans several days or weeks (such as a prolonged period of bad weather), should notice be given on day one (on a ‘just in case’ basis even though the duration and effect of the event are unknown) or at the end of the event (which the effect is known but with the risk the employer will say you have given notice too late?). These were the type of issues considered by the UK courts in the 2014 case of Obrascon Huarte Lain SA v Her Majesty’s Attorney General for Gibraltar[1] where the court said the notice provisions should be construed broadly, meaning the time should be calculated from when the contractor became aware (or should have become aware) of the delay, rather than from the date of the event itself.

Across the common law jurisdictions, the hardest line against time bars is taken in Australia, with the 2012 decision in Andrews v Australia and New Zealand Banking Group Ltd[2] that such time bars can be unenforceable as penalties.

The approach in civil code jurisdictions such as the GCC generally take the middle ground.

The UAE Civil Code neither expressly prohibits time bars nor enforces them.

Instead, prescribed time periods need to be read in the context of certain provisions of the UAE Civil Code including:

  • Article 106 – prohibiting the exercise of rights if the desired interest or result is disproportionate to the harm that will be suffered by the other party;
  • Article 246 – requiring the parties to act in good faith; and
  • Article 249 – prohibiting a party from exercising its rights in a manner that is oppressive or abusive

These provisions, read together, have the effect of meaning that time bars are neither expressly permitted nor expressly prohibited under UAE law. Instead, consideration will be given to matters which under common law are considered as being “equitable principles” such as whether the parties were acting in good faith, whether the actions are oppressive or unconscionable, and whether the benefit enjoyed by one party will be disproportionate to the harm suffered by the other party. Although such an approach is to be commended, since it ensures that a party is prevented from unnecessarily abusing its position under the contract, it does mean that the terms of the contract may be ignored in some instances. It is not clear as to the frequency at which courts in the UAE are willing to intervene and override the express terms of the contract, and this is an area we are continuing to monitor with interest.

Of course, a different scenario arises if a clause is silent on the consequences of a failure to submit a claim strictly in accordance with the time period prescribed by the construction contract. The question then becomes whether a time bar is implied when the prescribed steps to making a claim are not followed. One of the leading authorities on time-bars is Brember Handels GmbH v Vanden Avenne Izegem PVBA[3], HL which is authority for the proposition that, for a notice requirement clause to be a condition precedent, the clause must state the precise time for service and make it plain by express language that unless the notice is served within that time, the party required to give notice will lose its rights under that clause. Hence the conclusion should be that time bars will never be implied. However notably Jackson J in Multiplex Construction (UK) Ltd v Honeywell Control Systems[4] permitted a time bar to be implied despite the contract being silent on the matter. Some commentators however have suggested that a clear intention for a condition precedent is required, and that the decision in Multiplex can be distinguished on the basis of the Prevention Principle. Although there is no clear guidance in the UAE on whether a UAE court would be willing to view notice requirements as a condition precedent without clear words to that effect, in our view the UAE courts do not follow the principles which are equivalent to those in Brembar but instead weigh up the circumstances of each case and determine the fairest approach.


 

[1] [2014] EWHC 1028 (TCC)

[2] (2012) 290 ALR 595

[3] [1978] 2 Lloyd’s Rep 109

[4] [2007] EWHC 477 (TCC)

No Contract, No Problem: HICPA Does Not Prevent Contractors From Recovery Under A Quantum Meruit Theory

By  Jackie S. Celender and Leigh Argentieri Coogan, K&L Gates, Pittsburgh

I. HICPA Does Not Foreclose Contractors From Recovery Under A Theory Of Quantum Meruit.

The Supreme Court of Pennsylvania recently held that the Home Improvement Consumer Protection Act, 73 Pa. C.S. § 517.1-517.18 (“HICPA”), does not preclude a contractor from recovering under the theory of quantum meruit in the absence of a valid and enforceable home improvement contract.  Shafer Elec. & Const. v. Mantia, 96 A.3d 989 (Pa. 2014).  The decision affirmed the holding of the Superior Court of Pennsylvania, albeit on slightly different grounds.

Instead of focusing on the General Assembly’s intent (as the Superior Court of Pennsylvania did),[1] the Court relied on Durst v. Milroy General Contracting, Inc., 52 A.3d 357 (Pa. Super. 2012), holding that “the plain, unambiguous language of Section 517.7(g)[2] does not prohibit the cause of action in quantum meruit.”  Shafer Elec. & Constr., 96 A.3d at 996.  The Court noted that “[i]t is well settled at common law . . . that a party shall not be barred from bringing an action based in quantum meruit when one sounding in breach of express contract is not available,” and that “[w]hile traditional contract remedies may not be available due to the contractor’s failure to adhere to Section 517.7(a) . . . Section 517.7(g) does not contemplate the preclusion of common law equitable remedies such as quantum meruit when a party fails to comply with subsection (a).”  Id.  The Court concluded that “[i]f the General Assembly had seen it fit to modify the right of non-compliant contractors to recover in contract or quasi-contract, statutory or common law, or otherwise, it could have done so,” but did not.  Id.

The Court’s decision has important implications for contractors’ ability to use Pennsylvania’s mechanics’ lien law, 49 P.S. § 1101, et seq. as a tool in recovering unpaid amounts owed for work performed on a home improvement project.  In Pennsylvania, mechanics’ liens must be based on a contract, either express or implied.  See 49 P.S. § 1201 (defining “contractor” as one who, by contract with the owner, express or implied, erects, constructs, alters or repairs an improvement . . . or furnishes labor, skill or superintendence . . . or supplies or hauls materials, fixtures, machinery or equipment reasonably necessary for and actually used . . .”) (emphasis added).  The Court’s holding preserves a home improvement contractor’s ability to file and obtain a judgment on a mechanics’ lien based on an implied contract and in the absence of an express contract (i.e., where the contract does not comply with Section 517.7(a) of HICPA).

II. Quantum Meruit Allows Recovery Of The Value Of The Work Performed.

The Supreme Court of Pennsylvania’s decision in Shafer makes clear that contractors found to have an invalid home improvement contract under HICPA are still able to recover money for work performed by bringing a quasi-contract claim under a theory of quantum meruit.  Where a contractor is successful in bringing a cause of action in quantum meruit, the contractor is entitled to recover the value of the benefit conferred on the homeowners.  See, e.g., Durst, 52 A.3d at 360 (quoting Am. & Foreign Ins. Co. v. Jerry’s Sport Ctr., Inc., 2 A.3d 526, 532 n.8 (2010) (“Quantum meruit is an equitable remedy to provide restitution for unjust enrichment in the amount of the reasonable value of services.”) (citing Black’s Law Dictionary (8th ed. 2004))); Com., Dep’t of Pub. Welfare v. UEC, Inc., 397 A.2d 779, 782 (Pa. 1979) (amount owed under a quantum meruit theory was “the reasonable value of the services performed”).  As such, contractors should be prepared to prove the value of the services performed and materials provided on the project to recover under a theory of quantum meruit.  Although the cost of materials and labor expended is normally a good proxy for the value conferred on a particular project, contractors should be mindful that under certain circumstances the value conferred may exceed the contractors’ costs and that, in those circumstances, relying on the contractors’ costs may undervalue the contractors’ quantum meruit claim.

III. The Case Law Interpreting HICPA Is Scarce.

There is a relative lack of caselaw interpreting HICPA and stating under what circumstances HICPA should apply.  The legislative history of HICPA suggests that HICPA should not apply to all home improvement projects—in particular, those involving sophisticated homeowners (i) who have a contractor that fully performed, and (ii) who have obtained all of the benefits of the contract but have not complied with the burdens (i.e., payment).[3]  Given the undeveloped nature of the caselaw interpreting HICPA, contractors attempting to recover payment for unpaid work based on a home improvement contract should (if the facts permit) assert causes of action (or facts supporting causes of action) for both breach of contract and, in the alternative, quantum meruit recovery.

 

[1] The Superior Court of Pennsylvania focused its rationale on canons of statutory construction to ascertain legislative intent.  See Shafter Elec. & Constr., 96 A.3d at 996.

[2] Section 517.7(g) “Contractor’s recovery right,” provides:

Nothing in this section shall preclude a contractor who has complied with subsection (a) from the recovery of payment for work performed based on the reasonable value of services which were requested by the owner if a court determines that it would be inequitable to deny such recovery.

Shafer Elec. & Constr., 96 A.3d at 992.

[3] The General Assembly enacted HICPA to protect vulnerable consumers, such as the elderly, infirm, and first-time homebuyers from predatory contractors (i.e., contractors that abscond with homeowners’ money without completing the work).  See 2008 Pa.H.R. Jour., No. 65 p.2292 (Statement of Representative Preston) (“If you care about the senior citizens or the young couple who is buying a first-time starter house and they want to be able to remodel it and not be able to be ripped off,” then “I am going to ask [those] members…to support the Tomlinson bill.”); 2008 Pa.H.R. Jour., No. 64, p.2199 (Statement of Representative Marsico) (the Pennsylvania Legislature’s intent behind HICPA was to “address the problems of home improvement contractors who take people’s money and leave town without doing the work”).