Catagory:Case Summaries

1
Court Determines That A Builder May Seek Equitable Indemnity Against A Manufacturer Under California’s Right to Repair Act
2
Idaho’s High Court Analyzes 15 Factors for Determining Whether a Worker is an Independent Contractor or an Employee
3
Contractual Limitation of Liability in Engineer / Survey Contract Upheld
4
Foreign Contractor’s Failure to Register with Secretary of State Does Not Void Contract or Arbitration Clause
5
Inclusion of Disallowed Items in Lien Not Always Bad Faith
6
Court Rules Contractor’s Failure to File Action or Counterclaim to Enforce Lien within 20 days in Compliance with the Statute Requires Discharge of the Lien
7
Court Holds Action on Performance Bond Accrues Upon Contractor’s Acceptance of Subcontractor’s Work and Payment for that Work in Full
8
Court Rules Lien Timely Filed Pursuant to Florida Statute 713.08(5)
9
Insurer Granted Summary Judgment against General Contractor where Contract between Subcontractor and Injured Worker’s Firm Fails to Meet Indemnification Requirements
10
Inability to Determine Whether Owner Owed General Contractor when Subcontractor filed Lien Precludes Summary Judgment

Court Determines That A Builder May Seek Equitable Indemnity Against A Manufacturer Under California’s Right to Repair Act

Greystone Homes, Inc. v. Midtec, Inc. 168 Cal.App.4th 1194 (Cal. Ct. App. 2008)

California’s Right to Repair Act (Civil Code section 895 et. seq. or the “Act”) establishes a set of standards for residential construction and provides tort liability for failing to meet those standards. The Act was enacted in response to the California Supreme Court’s decision in Aas v. Superior Court, 24 Cal.4th 627, 636 (2000), which held that “[i]n actions for negligence, a manufacturer’s liability is limited to damages for physical injuries; no recovery is allowed for economic loss alone.” In other words, under Aas, the “economic loss rule” precluded recovery for damages such as “the difference between price paid and value received, and deviations from standards of quality that have not resulted in property damage or personal injury.” The Act, however, abrogated the Aas decision by permitting a homeowner that established a violation of the Act to recover economic losses from a builder, among others, without having to show that violation caused property damage or personal injury.

In the recent case of Greystone Homes, Inc. v. Midtec, Inc., the California Court of Appeal ruled on the following two issues that had not been previously addressed under the Act: (1) whether a builder may recover for economic loss caused by a product manufacturer’s violation of the Act through a claim for equitable indemnity against that manufacturer; and (2) whether that builder may bring a direct action for negligence against the manufacturer to recover its economic losses. As discussed below, the court concluded that a builder may bring an action for equitable indemnity to recover economic loss as a result of a manufacturer’s violation of the Act, but a direct claim for negligence is not permitted.

Read More

Idaho’s High Court Analyzes 15 Factors for Determining Whether a Worker is an Independent Contractor or an Employee

Excell Constr., Inc., v. Idaho Dep’t of Commerce and Labor, 145 Idaho 783, 186 P.3d 639 (2008)

This appeal arises out of an Idaho Industrial Commission finding that certain sheetrock workers hired by Excell Construction were employees rather than independent contractors.  At issue was whether Excell would be required to pay $6,353 in unemployment insurance taxes and penalties.  On appeal, the Idaho Supreme Court held the workers were independent contractors and reversed the Commission’s finding.

Read More

Contractual Limitation of Liability in Engineer / Survey Contract Upheld

Blaylock Grading Co., LLP v. Smith, 658 S.E.2d 680 (N.C. Ct. App. 2008)

In this case, a grading contractor sued a surveyor (who was also an engineer) for breach of contract and negligence regarding mistakes in surveying work which resulted in the contractor having to incur costs to import fill to raise the elevation of the site.  The contract between the contractor and surveyor contained a provision limiting the surveyor’s liability to $50,000.  The surveyor unsuccessfully moved for partial summary judgment based on the limit of liability.  Following a jury verdict against the surveyor for $574,714, the surveyor moved for judgment notwithstanding the verdict, which the trial court denied, ruling that the limit of liability was void as against public policy.  The North Carolina Court of Appeals reversed the trial court, holding that the limitation of liability was valid and enforceable.

Read More

Foreign Contractor’s Failure to Register with Secretary of State Does Not Void Contract or Arbitration Clause

City of Westfield v. Harris & Assocs. Painting, Inc., 567 F. Supp. 2d 252 (D. Mass. 2008)

In this case, the Federal District Court for the District of Massachusetts allowed a contractor’s motion to compel arbitration and remanded the case to arbitration despite the fact that the contractor failed to register as a foreign corporation with the Massachusetts Secretary of State as required by M.G.L. c. 30, § 39L.

Read More

Inclusion of Disallowed Items in Lien Not Always Bad Faith

Politano v. GPA Constr. Group, 2008 WL 515661 (Fla. Dist. Ct. App. Dec. 10, 2008)

In Politano, an owner moved to discharge a contractor’s lien for willful exaggeration based on the contractor’s inclusion of overhead and profit.  The Third DCA affirmed the trial court’s decision to reduce the amount of the lien accordingly, but not discharge the lien based on the finding that the disallowed items included in the lien were a result of mistake not willful exaggeration.  It rejected the owner’s argument that a lien is willfully exaggerated if it includes non-lienable items without regard to ignorance or good faith, or that a court’s reduction of a lien amount necessarily means the original lien amount was fraudulent.
 

Court Rules Contractor’s Failure to File Action or Counterclaim to Enforce Lien within 20 days in Compliance with the Statute Requires Discharge of the Lien

Brookshire v. GP Constr. of Palm Beach, Inc., 99 So.2d 179 (Fla. Dist. Ct. App. 2008)

In Brookshire, an owner filed a complaint to discharge a contractor’s lien and the clerk issued an order to show cause under Florida Statute Sec. 713.21(4).  Accordingly, the contractor had 20 days to show cause as to why his lien should not be enforced by action or vacated and cancelled of record.  Failure to do so would result in cancellation of the contractor’s lien.  The contractor filed a motion to compel arbitration and set it for hearing within the 20 day period, but did not respond to the show cause order.  The contractor argued that the motion to compel satisfied Section 713.21.  The appellate disagreed and directed the trial court to discharge the lien.

The contractor had argued that the motion to compel arbitration satisfied Section 713.21 because the dispute would ultimately be arbitrated and the contractor wanted to avoid any issue as to whether he was waiving arbitration.  The court held that Section 713.21 does not allow for exceptions, such as extensions of time, nor does it leave the court with any discretion to excuse a failure to comply.  The court also noted that any concern regarding waiving arbitration could have been satisfied by contemporaneously filing a motion to arbitrate those issues that were allegedly subject to arbitration.

Court Holds Action on Performance Bond Accrues Upon Contractor’s Acceptance of Subcontractor’s Work and Payment for that Work in Full

BDI Constr. Co. v. Hartford Fire Ins. Co., 2008 WL 4568075 (Fla. Dist. Ct. App. Oct. 15, 2008)

In BDI Construction Co., a subcontractor filed a third party action on a sub-subcontractor’s performance bond.  The surety moved for summary judgment claiming that the agreed five-year statute of limitations under Florida Statute Section 95.11(2)(b) began to run when the subcontractor accepted the sub-subcontractor’s work as complete and paid for the work in full.  The subcontractor on the other hand argued that the statute of limitations began to run when the entire project was completed and accepted by the owner.  The subcontractor relied on the Florida Supreme Court’s opinion in Fed. Ins. Co. v. Southwest Florida Retirement Ctr., Inc., 707 So. 2d 1119, 1121 (Fla. 1998), which stated that Section 95.11 “as it applies to an action on a performance bond, accrues on the date of acceptance of a project as having been completed according to the terms and conditions set out in the construction contract.”
 

Read More

Court Rules Lien Timely Filed Pursuant to Florida Statute 713.08(5)

J.S.L. Constr. Co. v. Levy, 994 So.2d 179 (Fla. Dist. Ct. App. 2008)

In this case, a homeowner sued a contractor to discharge a mechanic’s lien and for breach of contract.  The contractor was hired to construct the shell of a residence, with non-shell work performed by change order.  Among other things, this case addresses whether the contract recorded its claim of lien timely.

Florida Statutes Section 713.08(5) provides that a "claim of lien may be recorded at any time during the progress of the work or thereafter but not later than 90 days after the final furnishing of the labor or service or materials by lienor."  The parties had agreed that the contractor would oversee work performed by electrical and other subcontractors.  Moreover, because the subcontractors’ permits were tied to the master permit, the contractor could not close out its permit and complete the project until the electrical and other subcontract work was performed.  The contractor also did a final walk through of the project with the building inspector.  Because the contractor filed its claim of lien within 90 days of those activities, the claim of lien was timely.

Insurer Granted Summary Judgment against General Contractor where Contract between Subcontractor and Injured Worker’s Firm Fails to Meet Indemnification Requirements

Connolly Bros., Inc. v. Nat’l Fire & Marine Ins. Co., Civ. No. 06-11673-NG, 2008 WL 5423198 (D. Mass. Sept. 30, 2008)

In this case, the Federal District Court for the District of Massachusetts granted an insurer’s motion for summary judgment on a general contractor’s claim for indemnification and for unfair and deceptive practices under M.G.L. c. 93A, because the general contractor was not covered for the relevant incident by the insurer’s policy.

Read More

Inability to Determine Whether Owner Owed General Contractor when Subcontractor filed Lien Precludes Summary Judgment

In Nitro Dynamics v. Petruzzi Bros., Inc., 2008 WL 4635884 (Mass. Super. Ct. Sept. 26, 2008)

In this case, a subcontractor sued three defendants – the owner, the general contractor, and a surety – asserting claims for breach of contract, quantum meruit, and for recovery on a mechanic’s lien dissolution bond.  The Superior Court granted the owner’s motion for judicial notice of a stipulation of dismissal in a related action, but denied the owner’s motion for summary judgment.

Read More

Copyright © 2024, K&L Gates LLP. All Rights Reserved.