Catagory:Case Summaries

1
Judicial finding that plaintiff’s claims are not time-barred is not binding against a newly joined defendant
2
General Contractor’s Trust Fund Payments to Subcontractor Were Not Improper
3
Court rules on reasonable amount of collateral that contractor must provide to insurer of construction project
4
Surety That Did Not Fully Perform Could Not Succeed to Payment Rights
5
Court rules against contractor that wrongfully demanded early payment in contradiction of the payment schedule it signed
6
“Agreements to Agree” May Not be Enforceable
7
Failure to Provide all Necessary Minority and Woman-Owned Business Enterprise Subcontracts Within Reasonable Time After Subcontract Award is Material Breach of Contact
8
Fifth Circuit Disallows Equitable Defenses to Limitations Under Texas Performance Bond Statute
9
California Court of Appeal Clarifies Definition of Retention Payments Under Civil Code § 3260
10
Lien Held Invalid for Failure to Comply with Statutory Attestation Requirement

Judicial finding that plaintiff’s claims are not time-barred is not binding against a newly joined defendant

DeFilippo v. Knolls of Melville Redev. Co., No. 00-21112, 2010 WL 4904665 (Sup. Ct. Suffolk Co. Nov. 30, 2010)

In DeFilippo v. Knolls of Melville Redevelopment Co., a subcontractor employed the plaintiff, who sustained personal injuries while working.  Plaintiff originally brought suit against four defendants but lost at summary judgment.  Plaintiff then sought to amend his complaint to add a new defendant, Arlen Contracting Corp. Arlen argued that plaintiff’s claims against it were time barred by the three-year statute of limitations.  Plaintiff alleged that the claims should go forward because the lower court properly held that his claims were exempted from the statute of limitations.  The court disagreed and found that because Arlen did not have an opportunity to oppose plaintiff’s argument, as it was not a party to the lower court’s decision, Arlen would be given a chance to litigate the issue.

General Contractor’s Trust Fund Payments to Subcontractor Were Not Improper

Metro Found. Contractors, Inc. v. Marco Martelli Assocs., Inc., 78 A.D.3d 594, 912 N.Y.S.2d 187 (N.Y. App. Div. 2010)

In Metro Foundation Contractors, the Appellate Division, First Department, denied the plaintiff subcontractor’s motion for summary judgment, finding that fact issues remained as to whether the plaintiff defaulted under the subcontract and as to whether defendant general contractor’s payments to the plaintiff and to vendors were proper.  The court did hold that the defendant did not violate New York’s lien law in paying trust funds to the plaintiff and vendors, who were the proper beneficiaries.

Court rules on reasonable amount of collateral that contractor must provide to insurer of construction project

Safeco Ins. Co. v. M.E.S., Inc., No. 09-cv-3312, 2010 WL 4828103 (E.D.N.Y. Nov. 22, 2010)

In Safeco Ins. Co. v. M.E.S., Inc., the court decided which parameters should be considered when determining the amount of collateral to which an insurer of construction projects is entitled.  In this case, defendant construction companies executed indemnity agreements with plaintiff insurer.   Plaintiff sued to secure collateral under the indemnity agreements, arguing that it was entitled to several million dollars from each defendant as collateral security.  Defendants argued that the amounts should be reduced for several reasons, including (i) the fact that the insurer failed to revise its costs estimate to reflect the actual amounts of the subcontract awarded, and (ii) the insurer had several accounts receivable whose proceeds should be used to cover insurer’s costs.  The court agreed with the defendants on the first argument but not the second; the court determined the appropriate amount of collateral not by seeking mathematical certainty, but by applying New York’s reasonableness standard to construe the facts and the documentation submitted by the parties.

Surety That Did Not Fully Perform Could Not Succeed to Payment Rights

Mount Vernon City School Dist. v. Nova Cas. Co., 78 A.D.3d 1028, 912 N.Y.S.2d 98 (N.Y. App. Div. Nov. 23, 2010)

In Mount Vernon City School District, the plaintiff school district contracted with the defendant to provide heating, ventilation, and air conditioning work at a middle school.  The defendant secured a performance bond from the defendant surety.  Ultimately, the contractor failed to complete the work, and the surety refused to perform under the bond.  The district sued both the surety and the contractor for breach of contract.  The contractor had requested that payment be sent to the state Department of Labor, to be applied to a claim in another school district, and the surety argued that it should succeed to the contractor’s rights under its contract.

The Appellate Division, Second Department, disagreed, holding that the surety was not a fully paying and performing party, and that therefore it did not succeed to the rights of the payment beneficiaries.  Furthermore, the court held that the district did not breach the payment terms of the performance bond by paying the money over to the Department of Labor on request.  Finally, the court found that the school district was not entitled to attorney’s fees, since nothing in the parties’ agreements provided for such fees.

Court rules against contractor that wrongfully demanded early payment in contradiction of the payment schedule it signed

Remodeling Constr. Serv. v. Minter, 78 A.D.3d 1677, 913 N.Y.S.2d 446 (NY App. Div. 4th Dep’t Nov. 19, 2010)

In Remodeling Constr. Serv. v. Minter, a construction company was denied further payment where it demanded more payment than it was contractually owed.  Defendant hired plaintiff construction company to rebuild defendant’s house.  The parties agreed in writing that payment would be meted out according to a payment schedule.  According to the schedule, the drywall installation was a prerequisite to the fifth payment.  After completing all the work necessary to receive the first four payments, and having received the first four payments, plaintiff then refused to install the drywall.  Plaintiff refused to continue unless defendant paid plaintiff additional sums.  Defendant refused and plaintiff brought suit for breach of contract.  The court found that according to the contract, plaintiff was entitled only to the first four payments.  The court held that plaintiff breached the contract by refusing to perform and wrongfully demanding the fifth payment.  Plaintiff’s claim was dismissed.
 

“Agreements to Agree” May Not be Enforceable

By: Todd Reuter, K&L Gates, Spokane/Coeur D’Alene

Spokane Structures, Inc. v. Equitable Inv., LLC, 148 Idaho 616, 226 P.3d 1263 (2010)

"Agreements to agree" may not be enforceable.  Here, a contractor signed a one-page document entitled “Design/Build Agreement” that provided that the contractor would “design, engineer, and draft plans in preparation of all documents/drawings required to enable the owner and contractor to agree on a final design and cost of construction to be performed.”  The contractor presented a final design plan to the landowner, but the landowner decided not to follow through with the project.  The contractor sued for specific performance, trying to force the owner to pay him for work.

Read More

Failure to Provide all Necessary Minority and Woman-Owned Business Enterprise Subcontracts Within Reasonable Time After Subcontract Award is Material Breach of Contact

Jay Dee/Mole Joint Venture v. Mayor and City Council of Baltimore, 725 F. Supp. 2d 513 (D. Md. 2010)

In an interesting decision issued by the United States District Court for the District of Maryland, the Court held that a prime contractor was in material breach of its contact with the City of Baltimore for not entering into promised subcontracts with Minority and Women-Owned Disadvantaged Businesses.

Under Maryland law, state and local public contracts typically require participation by minority, social, economic and woman-owned disadvantaged businesses (collectively “DBs”).  Such participation is usually accomplished by subcontracts, which are typically entered into post prime contract award.  To qualify as a bidder/offeror, however, the prime contractor must make certain certifications and representations as to how the DB participation requirements are to be met.

Read More

Fifth Circuit Disallows Equitable Defenses to Limitations Under Texas Performance Bond Statute

Hartford Fire Ins. Co. v. City of Mont Belvieu, Texas, No. 09-40586 (5th Cir. July 13, 2010)

By:  David Coale & Billie Ann Maxwell, K&L Gates, Dallas

This case shows why it is important for governmental entities, their contractors, and performance bond providers to be aware of statements among the parties for limitations purposes, and the application of equitable defenses, in the context of the one-year limitations period under Texas Government Code § 2253.078(a).  The lessons of this case apply fully to similar statutes in other jurisdictions.

Read More

California Court of Appeal Clarifies Definition of Retention Payments Under Civil Code § 3260

Yassin v. Solis, 184 Cal. App. 4th 524 (Cal. Ct. App. 2010)

By: Carlo L. Rodes and Brett D. Bissett, K&L Gates, Los Angeles

In this case, the court of appeal set forth a definition for retention that applies whenever a contractor seeks an award of penalties for improperly withheld retention under a California prompt payment statute.

The plaintiff-contractor, Diaa Yassin was hired by the defendants-owners, (collectively “Solises”), to improve the Solises’ home.  Under the contract, Yassin was to receive a series of payments throughout various stages of construction and the last payment was to be made upon completion of the work and before occupancy.  Yassin ultimately sued the Solises for money allegedly owed under the contract.  Although the court addressed other matters, a principal issue was the status of the final two payments of $15,000 and whether those amounts qualified as retention payments under California Civil Code § 3260.  Under section 3260, if an owner fails to make retention payments within the time prescribed by that section, a contractor may recover a penalty in the amount of 2 percent per month on the improperly withheld amount plus attorney fees.

Read More

Lien Held Invalid for Failure to Comply with Statutory Attestation Requirement

Williams v. Athletic Field, Inc., No. 33607-3-II (Wash. Ct. App. Apr. 7, 2010)

By: Jesse O. Franklin IV and Bradley D. Bowen, K&L Gates, Seattle

This case demonstrates the importance for claimants to substantially comply with Washington’s lien statutes.  The issue in Williams was whether a lien is invalid if a lien filing service employee signs the lien’s attestation clause, rather than a claimant or the claimant’s attorney.  The Court in Williams held that an agent of a claimant can sign a lien’s attestation clause under RCW 60.04.091, addressing the recording of liens, including an employee of a lien filing service.  However, the Court went on to hold that when the claimant’s agent is also a corporation, like a lien filing service, the agent must comply with the corporate acknowledgement requirements under Washington law.  Moreover, the Williams case stands for the more general proposition that a lien claimant in Washington must clearly demonstrate that all statutory lien claim requirements have been met because courts strictly construe the lien statutes.

Read More

Copyright © 2024, K&L Gates LLP. All Rights Reserved.