Catagory:Europe

1
FIDIC Update: Clarity on Notice Provisions and Time Bars
2
Welcome to the 26th Edition of K&L Gates’ Arbitration World
3
Welcome to the 24th Edition of K&L Gates’ Arbitration World
4
Welcome to the 23rd Edition of K&L Gates’ Arbitration World
5
The Projects and Construction Review, Chapter 22 “Italy”
6
Welcome to the 22nd Edition of K&L Gates’ Arbitration World
7
Welcome to the 21st Edition of K&L Gates’ Arbitration World
8
Welcome to the 20th Edition of K&L Gates’ Arbitration World
9
K&L Gates’ Arbitration World, June 2012
10
K&L Gates’ Arbitration World, March 2012

FIDIC Update: Clarity on Notice Provisions and Time Bars

By Mike R. Stewart and Camilla A. de Moraes, K&L Gates, London

 

Case law on the FIDIC form of contract has to-date been scarce, particularly in respect of Sub-Clause 20.1.

The recent case of Obrascon Huarte Lain SA v Her Majesty’s Attorney General for Gibraltar [2014] EWHC 1028 (TCC) gives an interesting judicial insight into the interpretation of Sub-Clause 20.1 as well as Sub-Clauses 4.12 (Unforeseeable Physical Conditions) and 15 (Termination).

The case was brought by the Contractor, Obrascon Huarte Lain (OHL), who was engaged to undertake the design and construction of a road and tunnel under the runway of Gibraltar airport. Subject to some minor amendments, the contract was based on the FIDIC Yellow Book.

The main issue for the court to determine related to the validity of the termination of the contract by the Employer, the Government of Gibraltar. The court also considered the Contractor’s compliance with Sub-Clause 20.1 in respect of extension of time claims brought for the discovery of rock and exceptionally adverse weather (pursuant to Sub-Clause 4.12).

Sub-Clause 20.1
Sub-Clause 20.1 must be complied with where the Contractor “considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract…

The requirement is that the Contractor must notify the engineer, describing the event or circumstance giving rise to the claim “as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance.” [emphasis added]

If the Contractor fails to give notice of a claim within the 28-day period, he shall not be entitled to an EOT or any additional payment and the Employer shall have no liability in respect of such claim.

The 28-day period referred to within Sub-Clause 20.1 does not run from the occurrence of the event or circumstance giving rise to the claim. Instead, it runs from when the Contractor “became aware, or should have become aware, of the event or circumstance” giving rise to the claim.

Less clear is whether the 28-day period starts running when the Contractor is aware (or is deemed to be aware) of (i) the event or circumstance or (ii) the fact that the event or circumstance is to have time and/or cost consequences such that he is entitled to an EOT or additional payment.

In his judgement, Mr Justice Akenhead saw no reason why Clause 20.1 should be construed strictly against the Contractor, especially given the serious consequences of such an approach, namely that the Contractor would lose entitlement to what otherwise might be a good claim against the Employer.

Mr Justice Akenhead, in reaching his decision, made reference to Sub-Clause 8.4 of the FIDIC conditions, which sets out the circumstances in which the Contractor is entitled to an extension of time. Sub-Clause 8.4 states that:

The Contractor shall be entitled subject to Sub-Clause 20.1…to an extension of the Time for Completion if and to the extent that the completion for the purposes of Sub-Clause 10.1…is or will be delayed by any of the following causes…” [emphasis added]

The judge placed particular emphasis on the words identified in bold in the paragraph above. He stated that the entitlement to an extension clearly arises either when it is clear that there will be a delay (a prospective delay) or when the delay has at least started to be incurred (a retrospective delay). From this, he concluded that notice does not have to be given until there actually is a delay.
Whilst of course the Contractor can give notice when it reasonably believes that it will be delayed, it is not required to do so. Sub-Clause 8.4 grants the Contractor the choice by virtue of the word “or” between “is” and “will be.” If the Contractor was required to give notice on the earlier date, the wording of Sub-Clause 8.4 would have read “is or will be delayed whichever is the earliest” [emphasis added].

Further, the judge held that whilst there is no particular form of notice required pursuant to Sub-Clause 20.1, it must be recognisable as a “claim”. In this case, OHL had tried to rely on a monthly progress report which stated that “The adverse weather condition (rain) have [sic] affected the works” to constitute the requisite notice for an extension of time. In the judge’s view, this was “clearly nowhere near a notice under Clause 20.1.”

Mr Justice Akenhead confirmed that the onus is on the Employer to establish that a notice is not given in time. In any event, in this particular case, OHL failed to give notice of the exceptionally adverse weather within the 28-day period and, therefore, was only entitled to a one-day extension to the Time for Completion.

Sub-Clause 4.12 (Unforeseeable Physical Conditions)
The court, in determining whether OHL had encountered unforeseeable physical conditions, was required to consider the ground conditions that were reasonably foreseeable by an experienced Contractor at the date of the submission of the tender. OHL had been provided with site data, and had been told to allow for a substantial volume of contaminated material, but had not done so.

The court held that OHL should have carried out “some intelligent assessment and analysis” of why the site was contaminated and what the real risk was of encountering more contaminated material than had been envisaged at the tender stage. OHL had failed to do so and, therefore, its claims were rejected.

Sub-Clause 15 (Termination)
The court also had to consider whether the Employer had lawfully terminated the contract with OHL. Sub-Clause 15 provides that the Employer is entitled to terminate the contract if the Contractor (having been given notice) does not rectify a failure to carry out any obligation under the contract. The court held that Sub-Clause 15 is generally to be construed as permitting termination for significant or substantial breaches, rather than trivial or insignificant ones, but rejected OHL’s argument that the breach relied upon must be equivalent to a repudiatory breach of contract.

The court ultimately found in the Employer’s favour with regards to the lawfulness of the termination. Amongst other things, this was on the basis that OHL failed to progress the Works with due expedition, thereby breaching Clause 8.1 of the Contract. This allowed the Employer to terminate under 15.2(c) and recover all costs associated with the termination and completion costs, insofar as the same exceeded OHL’s original contract price. The award is likely to be the largest ever awarded to the Government of Gibraltar and will, therefore, have significant economic consequences, not least that it should be able to finalise the works commenced by OHL and have a working tunnel under the runway.

Conclusion
This recent case provides welcome clarity with respect to a number of matters.

Most importantly it highlights that, under Sub-Clause 20.1 of the FIDIC conditions, the clock does not start running for the Contractor until the date on which he is aware (or should have been aware) of the delay resulting from a particular event or circumstance. Although the court only considered Sub-Clause 20.1 in respect of an extension of time, the same principle is expected to apply to claims for additional payment made pursuant to this provision.

Claims made pursuant to Sub-Clause 20.1 must be identifiable as claims, with a description of the event or circumstance relied on, and must state that the notice is intended to notify a claim for an extension of time or additional payment under the contract. A passing reference to a particular event will not, on its own, be sufficient. However, it is important to note that whilst this judgment is likely to be viewed as positive for Contractors, it is certainly not carte blanche for the Contractor to disregard the notice provisions all together. He still has to comply with the 28-day period; it simply starts a little later.

Welcome to the 26th Edition of K&L Gates’ Arbitration World

Welcome to the 26th edition of Arbitration World, a publication from K&L Gates’ International Arbitration Group that highlights significant developments and issues in international and domestic arbitration for executives and in-house counsel with responsibility for dispute resolution.

To view Arbitration World, click here

To download a printable PDF of the publication, open the link above and click on the fourth icon from the right in the magazine toolbar at the top of the page. 
In this edition, we report on the much-anticipated decision of the U.S. Supreme Court in BG Group PLC v. Republic of Argentina regarding the respective roles of courts and arbitrators in deciding threshold issues of arbitrability or jurisdiction. We review a recent decision of the Indian Supreme Court in the context of the wider changes in India regarding international arbitration in recent years, as well as a decision of the Full Federal Court of Australia regarding the implications of seeking to resist enforcement of an award after already unsuccessfully challenging the award at the seat of arbitration.
We include articles on the new arbitration rules issued by the Japan Commercial Arbitration Association (JCAA) and the Vienna International Arbitration Centre (VIAC) and report on the interesting development of the introduction of “Optional Appellate Arbitration Rules” by the American Arbitration Association (AAA) / International Centre for Dispute Resolution (ICDR).
We consider the potential issues that may arise with short-form ‘ad hoc’ arbitration clauses, and continue our series of articles on means of protecting foreign investments with a review of the means of access to relevant dispute resolution mechanisms. We also provide our usual updates on developments from around the globe in international arbitration and investment treaty arbitration.
We hope you find this edition of Arbitration World of interest, and we welcome any feedback (email ian.meredith@klgates.com or peter.morton@klgates.com).

Welcome to the 24th Edition of K&L Gates’ Arbitration World

Welcome to the 24th edition of Arbitration World, a publication from K&L Gates’ International Arbitration Group that highlights significant developments and issues in international and domestic arbitration for executives and in-house counsel with responsibility for dispute resolution.

To view Arbitration World in our online magazine format, click here.

To download a printable PDF of the publication, open the link above and click  on the far right icon in the magazine toolbar at the top of the page.

This edition focusses on Africa, a continent that offers significant opportunities across a number of business sectors, and which is seeing remarkable GDP growth rates in many of its nation states.  We include a commentary on the means of mitigating risks arising from disputes when concluding business transactions in Africa.  We review the recent changes in the arbitration landscape in Africa and their potential impact.  We also include a comparative review of Maghreb’s arbitration laws, with particular focus on Morocco, Algeria and Tunisia.

We provide our usual update on developments from around the globe in international arbitration and investment treaty arbitration.  We look at recent U.S. court decisions on the evolving issue of class arbitration, continue our series of articles on means of protecting foreign investments with a review of the fair and equitable treatment protection standard, and consider the approach to multi-tiered dispute resolution provisions in different jurisdictions.  We hope you find this edition of Arbitration World of interest, and we welcome any feedback (email Ian.Meredith@klgates.com or
Peter.Morton@klgates.com).

Welcome to the 23rd Edition of K&L Gates’ Arbitration World

Welcome to the 23rd edition of Arbitration World, a publication from K&L Gates’ International Arbitration Group that highlights significant developments and issues in international and domestic arbitration for executives and in-house counsel with responsibility for dispute resolution.

To view Arbitration World, click here.

To download a printable PDF of the publication, open the link above and click on the far right icon in the magazine toolbar at the top of the page.

We are delighted to be able to include in this edition a guest contribution from Wieger Wielinga of Omni Bridgeway, funder and manager of cross border claim recoveries.  In his article, Wieger offers his insights and practical tips for the enforcement of arbitral awards against sovereign states and entities under their control, advising that parties overlook at their peril the potential risks and pitfalls of enforcement of awards.

We also include in this edition our usual update on developments from around the globe in international arbitration and investment treaty arbitration, along with specific articles covering some of those developments, along with other topics of interest in more detail, authored by members of K&L Gates’ International Arbitration Group.

We hope you find this edition of Arbitration World of interest, and we welcome any feedback (email ian.meredith@klgates.com or peter.morton@klgates.com).

The Projects and Construction Review, Chapter 22 “Italy”

Third Edition, Law Business Research Ltd.

Chapter 22 by: Francesco Sanna, Anna Amprimo and Carolina Teresa Arroyo, K&L Gates, Milan

I INTRODUCTION

The current state of Italian project finance is the result of a trend initiated more than 20 years ago, when public resources started to become scarce and the construction or infrastructure needed private funds to be carried out.

First came the realisation of energy plants – especially the renewables sector with the CIP6 regulation, which started in 1992 – where project finance started to be used in Italy on the basis of the UK experience.  Such project finance schemes were initially purely private and fostered by public subsidies in the sale of green energy to the state. In the light of the success of such structures, the Italian state in the late 1990s passed a specific regulation to use project finance schemes to finance, build and operate public infrastructures in the context of European framework legislation on public works.  The procedure, in brief, provided that private sponsors could submit autonomously to the authorities’ projects to finance, build and operate public infrastructure.

In the case of ‘cold’ infrastructure, public grants are available to subsidise business plans; public subsidies, however, need to comply with Eurostat rules and need only cover a minority part of the investment.  This procedure has passed through many legislative changes in the past decade and is now regulated under Article 153 et seq. of the Italian Act for Public Works, which provides a specific procedure for selecting sponsors in public PFI schemes.  Such schemes are extensively utilised in a wide range of infrastructures in Italy, with particular focus on hospitals and roads.  Purely private PFI schemes are still used in the energy sector, with a specific focus on renewable and photovoltaic projects.

These schemes are financed by major Italian banks, and their development has been helped by the setting up of regional public agencies that direct and manage all the major public PFI schemes dealing with infrastructure, but also urban regeneration programmes that involve the disposal of public assets.

(Footnotes omitted.)

To read the full chapter, click here.

Reproduced with permission from Law Business Research Ltd.
This article was first published in The Projects and Construction Review, 3rd edition (published in July 2013 – editor Júlio César Bueno).
For further information please email
Adam.Sargent@lbresearch.com 

Welcome to the 22nd Edition of K&L Gates’ Arbitration World

Welcome to the 22nd edition of Arbitration World, a publication from K&L Gates’ International Arbitration Group that highlights significant developments and issues in international and domestic arbitration for executives and in-house counsel with responsibility for dispute resolution.

To view Arbitration World in our new online magazine format, click here.

To download a printable PDF of the publication, open the link above and click on the far right icon in the magazine toolbar at the top of the page.

We are delighted to be able to include in this edition a guest contribution from Rubini Ventouras, Group Executive Legal Affairs, Asia Pacific, of Newmont Mining Corporation.  In her article, Rubini offers her perspectives on the challenges associated with the management of disputes in multiple, widely varying jurisdictions and explains why arbitration remains her preferred process for the resolution of international commercial disputes.

We are also pleased to welcome a contribution from James Blick, Director at TheJudge Limited, a leading broker of litigation and arbitration funding and after-the-event insurance.  In his article, James offers some practical tips and insights on how to get the best deal when negotiating with potential third-party sources of funding for arbitration.

This edition also includes our usual update on developments from around the globe in both international commercial arbitration and investment treaty arbitration, along with specific articles covering some of those developments and other topics of interest in more detail, authored by members of K&L Gates’ International Arbitration Group.  This edition includes a contribution from our new colleagues in Melbourne, Australia (following the combination of K&L Gates LLP with Middletons, effective 1 January 2013) describing a recent constitutional challenge to the international arbitration regime in Australia.

We hope you find this edition of Arbitration World of interest, and we welcome any feedback (email ian.meredith@klgates.com or peter.morton@klgates.com).

Welcome to the 21st Edition of K&L Gates’ Arbitration World

Welcome to the 21st edition of Arbitration World, a publication from K&L Gates’ International Arbitration Group that highlights significant developments and issues in international and domestic arbitration for executives and in-house counsel with responsibility for dispute resolution.

We are delighted to be able to include in this edition a guest contribution from David Burt, Corporate Counsel for E.I. du Pont de Nemours and Company (DuPont).  In his article, David describes the way in which DuPont’s “Global ADR Guide”, for use by DuPont’s 200 in-house lawyers across the world, came to be developed.

We are also pleased to include an article by Mick Smith, Partner & Co-Founder of Calunius Capital LLP, one of the leading providers of third party funding.  Third party funding is becoming ever more prevalent in both litigation and arbitration. In his article, Mick describes the processes of case assessment and case monitoring from the funder’s perspective.  This is the first of what will be a short series of articles on the important topic of third party funding in international arbitration.

We also include in this edition our usual update on developments from around the globe in international arbitration and investment treaty arbitration, along with specific articles covering some of those developments and other topics of interest in more detail, authored by members of K&L Gates’ International Arbitration Group.

We hope you find this edition of Arbitration World of interest, and we welcome any feedback (email ian.meredith@klgates.com or peter.morton@klgates.com).

In this Issue:

• DuPont Navigates ADR Worldwide
• News from around the World
• World Investment Treaty Arbitration Update
• Third Party Funding: Case Assessment and Monitoring
• U.S. Supreme Court Fires Shot across Oklahoma’s Bow
• What Qualifies as an Investment? A Primer on Protecting Foreign Investments (Part 2)
• Astro: Affirming Singapore’s Position on Challenging Awards on Jurisdictional Grounds
• No Dispute About It – Dispute Boards are Hot in Chinese Construction Projects
• A Comparative Analysis of the “Choice of Law” Approaches to Privilege in International Proceedings
• UAE Arbitration Insight – New York Convention Shifts Enforcement Approach

To view the entire edition, click here.

Welcome to the 20th Edition of K&L Gates’ Arbitration World

From the Editors

Welcome to the 20th edition of Arbitration World, a publication from K&L Gates’ International Arbitration Group that highlights significant developments and issues in international and domestic arbitration for executives and in-house counsel with responsibility for dispute resolution.

We are delighted that this edition includes a guest contribution from Abhijit Mukhopadhyay, President (Legal) of the Hinduja Group.  In his article, Abhijit offers his thoughts and perspectives on the topical subject of arbitration in India.  This represents what we expect to be the first of a number of guest contributions from in-house counsel in future editions of Arbitration World.

We hope you find this edition of Arbitration World of interest, and we welcome any feedback (email ian.meredith@klgates.com or peter.morton@klgates.com).

In this Issue:

  • Indian Arbitration: Recent Trends
  • News from around the World
  • World Investment Treaty Arbitration Update
  • International Arbitration in Chile—2004 and Beyond
  • Thailand Loses U.S. Appeal of Confirmation of UNCITRAL Award and Challenge to Arbitrability
  • Important UK Privy Council Decision on Enforcement Against State-Owned Entities
  • Saudi Arabia Introduces a New Arbitration Law
  • The Democratic Republic of the Congo Joins OHADA and its Arbitration Mechanisms
  • Developments at CIETAC – The New Arbitration Rules 2012 and the Rift with the Shanghai and Shenzhen Sub-Commissions
  • The Revised 2012 Swiss Rules
  • ‘Asymmetric’ Dispute Resolution Clauses: A Recent Russian Decision
  • New York Courts Offer Further Support for Parties to International Arbitrations
  • New Arbitration Rules in Poland: Lewiatan Court of Arbitration
  • Pioneering Deep Sea Mining Project Heads to Arbitration Signalling a New Type of Extractive Sector Dispute
  • What’s Done is Done – Or is it? Res Judicata in Domestic and International Arbitrations in the context of Insurance Coverage Disputes
  • Investment Treaty Arbitration in Africa: Summary Overview

To view the entire edition, click here.

K&L Gates’ Arbitration World, June 2012

From the Editors

Welcome to the 19th edition of Arbitration World, a publication from K&L Gates’ Arbitration Group that highlights significant developments and issues in international and domestic arbitration for executives and in-house counsel with responsibility for dispute resolution.

We hope you find this edition of Arbitration World of interest, and we welcome any feedback (email ian.meredith@klgates.com or peter.morton@klgates.com).

In this Issue:

  • News from around the World
  • World Investment Treaty Arbitration Update
  • U.S. Supreme Court Takes Another Look at the Enforceability of Pre-Dispute Arbitration Clauses
  • The “SCC Emergency Arbitrator”: First Experiences with the Pre-Arbitral Interim Relief Procedure
  • Guidance from the U.S. Second Circuit on Application of the Evident Partiality Standard
  • Early Case Assessment: A Litigation Arrow in an Arbitration Quiver
  • English Court Decides that Arbitration Agreement is Governed by Law of Seat of Arbitration and Prevails over Exclusive Jurisdiction Clause
  • International Arbitration: Developments from Singapore
  • Unsolved Mystery: Colombia’s International Arbitration Law
  • Who Qualifies as an Investor? A Primer on Protecting Foreign Investments (Part 1)
  • Developments in International Arbitration in Mauritius
  • The Chamber of Arbitration of Milan and the “Mediterranean Project”
  • Eurozone Exits: Possible Impact on Commercial Contracts
  • U.S. Ninth Circuit to Consider Who Decides Arbitrability When Arbitration Clause Incorporates UNCITRAL Rules But Includes Carve-Outs

To view the entire June 2012 edition, click here.

K&L Gates’ Arbitration World, March 2012

Emerging Markets Special Edition

Welcome to the 18th edition of Arbitration World, a publication from K&L Gates’ Arbitration Group.  This special edition focuses on issues and recent developments in emerging markets.  We also include our usual round-up of news items in international commercial arbitration and investment treaty arbitration.

We hope you find this edition of Arbitration World of interest, and we welcome any
feedback (email ian.meredith@klgates.com or peter.morton@klgates.com).

In this issue:

  • News from around the World
  • World Investment Treaty Arbitration Update
  • Developments in Indian Arbitration
  • Harmonizing Arbitration in China with International Best Practice
  • Arbitration in Ukraine – Moving Forward
  • Recent Developments on Arbitrability in Russia
  • The Arbitration Landscape in Latin America

View the entire March 2012 edition here.

Copyright © 2024, K&L Gates LLP. All Rights Reserved.